Share:


An analytic network process based risk assessment model for PPP hydropower investments

    Emre Caner Akcay Affiliation

Abstract

The number of public-private partnership (PPP) projects has gone up especially in developing countries. The risk assessment of PPP projects is essential in ensuring project success. The objective of this study is to develop an Analytic Network Process (ANP) based risk assessment model for hydropower investments, and a tool to facilitate quantification of risk ratings based on this model. The results show that the three most important risk factors that affect the overall risk rating of a PPP hydropower investment are legal risks, contractor/subcontractor risks, and operator risks. In addition, the three most important risk clusters were identified as stakeholders, government requirements, and resources, whereas market was the least important cluster. The tool that measures the risk rating of a PPP of hydropower project was tested on ten real cases, and satisfactory results were obtained in terms of its predictive capability. The contributions of this research include (1) identification of the risk factors and clusters of factors associated with PPP hydropower investments; (2) determination of the priority of each risk factor and cluster; (3) development a tool that guides the investors through the risk assessment of PPP hydropower investments.

Keyword : renewable energy, PPP, hydropower investment, ANP

How to Cite
Akcay, E. C. (2021). An analytic network process based risk assessment model for PPP hydropower investments. Journal of Civil Engineering and Management, 27(4), 268-277. https://doi.org/10.3846/jcem.2021.14650
Published in Issue
Apr 27, 2021
Abstract Views
989
PDF Downloads
730
Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

References

Ahmadabadi, A. A., & Heravi, G. (2019). The effect of critical success factors on project success in public-private partnership projects: A case study of highway projects in Iran. Transport Policy, 73, 152–161. https://doi.org/10.1016/j.tranpol.2018.07.004

Aladağ, H., & Işik, Z. (2018). The effect of stakeholder-associated risks in mega-engineering projects: A case study of a PPP airport project. IEEE Transactions on Engineering Management, 67(1), 174–186. https://doi.org/10.1109/TEM.2018.2866269

Aladağ, H., & Işik, Z. (2019). Design and construction risks in BOT type mega transportation projects. Engineering, Construction and Architectural Management, 26(10), 2223–2242. https://doi.org/10.1108/ECAM-08-2018-0351

Ameyaw, E. E., & Chan, A. P. C. (2015). Evaluation and ranking of risk factors in public-private partnership water supply projects in developing countries using fuzzy synthetic evaluation approach. Expert Systems with Applications, 42(12), 5102–5116. https://doi.org/10.1016/j.eswa.2015.02.041

Ashuri, B., Kashani, H., Molenaar, K. R., Lee, S., & Lu, J. (2012). Risk-neutral pricing approach for evaluating BOT highway projects with government minimum revenue guarantee options. Journal of Construction Engineering and Management, 138(4), 545–557. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000447

Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25–35. https://doi.org/10.1016/j.ijproman.2004.04.006

Bu-Qammaz, A. S., Dikmen, I., & Birgonul, M. T. (2009). Risk assessment of international construction projects using the analytic network process. Canadian Journal of Civil Engineering, 36(7), 1170–1181. https://doi.org/10.1139/L09-061

Chan, A. P. C., Yeung, J. F. Y., Yu, C. C. P., Wang, S. Q., & Ke, Y. (2011). Empirical study of risk assessment and allocation of public-private partnership projects in China. Journal of Management in Engineering, 27(3), 136–148. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000049

Cheng, E., & Li, H. (2004). Contractor selection using the analytic network process. Construction Management and Economics, 22(10), 1021–1032. https://doi.org/10.1080/0144619042000202852

Choma, A. A. (2008). How to reduce risks in contractors’ management. In PMI® Global Congress 2008, North America, Denver, CO. Project Management Institute, Newtown Square, PA.

Chou, J., & Pramudawardhani, D. (2015). Cross-country comparisons of key drivers, critical success factors and risk allocation for public-private partnership projects. International Journal of Project Management, 33, 1136–1150. https://doi.org/10.1016/j.ijproman.2014.12.003

Dehdast, G., Zin, R. M., Ferwati, M. S., Abdullahi, M. M., Keyvanfar, A., & McCaffer, R. (2017). DEMATEL-ANP risk assessment in oil and gas construction projects. Sustainability, 9, 1420. https://doi.org/10.3390/su9081420

Dikmen, I., Birgonul, M. T., & Ozorhon, B. (2007). Project appraisal and selection using the analytic network process. Canadian Journal of Civil Engineering, 34(7), 786–792. https://doi.org/10.1139/l07-006

Do, S. T., Likhitruangsilp, V., Kiet, T. T., & Nguyen, P. T. (2017). Risk assessment for international construction joint ventures in Vietnam. International Journal of Advanced and Applied Sciences, 4(6), 104–114. https://doi.org/10.21833/ijaas.2017.06.015

El-Abbasy, M. S., Zayed, T., Ahmed, M., Alzraiee, H., & Abouhamad, M. (2013). Contractor selection model for highway projects using integrated simulation and analytic network process. Journal of Construction Engineering and Management, 139(7), 755–767. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000647

Erdem, D., & Ozorhon, B. (2015). Assessing real estate project success using an Analytic Network Process. Journal of Management in Engineering, 31(4), 04014065. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000281

Ghorbani, A., Ravanshadnia, M., & Nobakht, M. B. (2014). A survey of risks in public private partnership highway projects in Iran. In 2014 International Conference on Construction and Real Estate Management, Kunming, China. https://doi.org/10.1061/9780784413777.058

Hasnain, M., Thaheem, M. J., & Ullah, F. (2018). Best value contractor selection in road construction projects: ANP-based decision support system. International Journal of Civil Engineering, 16, 695–714. https://doi.org/10.1007/s40999-017-0199-2

Hwang, B., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31, 424–433. https://doi.org/10.1016/j.ijproman.2012.08.003

Ibrahim, A. D., Price, A. D. F., & Dainty, A. R. J. (2006). The analysis and allocation of risks in public private partnerships in infrastructure projects in Nigeria. Journal of Financial Management of Property and Construction, 11(3), 149–163. https://doi.org/10.1108/13664380680001086

Karim, N. A. A. (2011). Risk allocation in Public-Private Partnership (PPP) project: A review on risk factors. International Journal of Sustainable Construction Engineering & Technology, 2(2), 8–16.

Keers, B. B. M., & Fenema, P. C. V. (2018). Managing risks in public-private partnership formation projects. International Journal of Project Management, 36, 861–875. https://doi.org/10.1016/j.ijproman.2018.05.001

Ke, Y., Wang, S., Chan, A. P. C., & Lam, P. T. I. (2010). Preferred risk allocation in China’s Public Private Partnership (PPP) projects. Journal of Project Management, 28, 482–492. https://doi.org/10.1016/j.ijproman.2009.08.007

Kumar, L., Jindal, A., & Velaga, N. R. (2018). Financial risk assessment and modelling of PPP based Indian highway infrastructure projects. Transport Policy, 62, 2–11. https://doi.org/10.1016/j.tranpol.2017.03.010

Kuru, K., & Artan, D. (2020). A canvas model for risk assessment and performance estimation in public-private partnerships. International Journal of Construction Management, 20(6), 704–719. https://doi.org/10.1080/15623599.2020.1763898

Li, H., Dong, K., Jiang, H., Sun, R., Guo, X., & Fan, Y. (2017). Risk assessment of China’s overseas oil refining investment using a fuzzy-grey comprehensive evaluation method. Sustainability, 9, 696. https://doi.org/10.3390/su9050696

Li, Y., & Wang, X. (2019). Using fuzzy analytic network process and ISM methods for risk assessment of public-private partnership: A China perspective. Journal of Civil Engineering and Management, 25(2), 168–183. https://doi.org/10.3846/jcem.2019.8655

Liu, J., Love, P. E. D., Smith, J., Regan, M., & Davis, P. R. (2015). Life cycle critical success factors for public-private partnership infrastructure projects. Journal of Management in Engineering, 31(5), 04014073. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000307

Mazher, K. M., Chan, A. P. C., Zahoor, H., Khan, M. I., & Ameyaw, E. E. (2018). Fuzzy integral-based risk-assessment approach for public-private partnership infrastructure projects. Journal of Construction Engineering and Management, 144(12), 04018111. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001573

Meade, L. M., & Presley, A. (2002). R&D project selection using the analytic network process. IEEE Transactions on Engineering Management, 49(1), 59–66. https://doi.org/10.1109/17.985748

Nguyen, A., Mollik, A., & Chih, Y. (2018). Managing critical risks affecting the financial viability of public-private partnership projects: Case study of toll road projects in Vietnam. Journal of Construction Engineering and Management, 144(12), 05018014. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001571

Niemira, M. P., & Saaty, T. L. (2004). An analytical network process model for financial-crisis forecasting. International Journal of Forecasting, 20(4), 573–587. https://doi.org/10.1016/j.ijforecast.2003.09.013

Osei-Kyei, R., & Chan, A. (2015). Review of studies on the critical success factors for public–private partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335–1346. https://doi.org/10.1016/j.ijproman.2015.02.008

Ozcan-Deniz, G., & Zhu, Y. (2015). A multi-objective decisionsupport model for selecting environmentally conscious highway construction methods. Journal of Civil Engineering and Management, 21(6), 733–747. https://doi.org/10.3846/13923730.2014.893915

Ozorhon, B., Dikmen, I., & Birgonul, M. T. (2007). Using analytic network process to predict the performance of international construction joint ventures. Journal of Management in Engineering, 23(3), 156–163. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:3(156)

Palaco, I., Park, M. J., Kim, S. K., & Rho, J. J. (2019). Public–private partnerships for e-government in developing countries: An early stage assessment framework. Evaluation and Program Planning, 72, 205–218. https://doi.org/10.1016/j.evalprogplan.2018.10.015

Saaty, T. L. (1994). How to make a decision: The analytic hierarchy process. Interfaces, 24(6), 19–43. https://doi.org/10.1287/inte.24.6.19

Saaty, T. L. (1996). Decision making with dependence and feedback: The analytic network process. Pittsburgh: RWS Publications.

Saaty, T. L. (2003). Decision-making with the AHP: Why is the principal eigenvector necessary? European Journal of Operational Research, 145(1), 86–91. https://doi.org/10.1016/S0377-2217(02)00227-8

Saaty, T. L. (2004). Fundamentals of the analytical network process-dependence and feedback in decision-making with a single network. Journal of Systems Science and Systems Engineering, 13(2), 129–157. https://doi.org/10.1007/s11518-006-0158-y

Saaty, T. L. (2008). Decision making with the analytic hierarchy process. International Journal of Services Sciences, 1(1), 83–98. https://doi.org/10.1504/IJSSCI.2008.017590

Shang, J. S., Tjader, Y., & Ding, Y. (2004). A unified framework for multicriteria evaluation of transportation projects. IEEE Transactions on Engineering Management, 51(3), 300–313. https://doi.org/10.1109/TEM.2004.830848

Shao, Y., Yuan, J., & Li, Q. (2016). Identification of the residual value risk factors for road PPP projects in China: Questionnaire survey and analysis. Proceedings of the 20th International Symposium on Advancement of Construction Management and Real Estate, 379–389. https://doi.org/10.1007/978-981-10-0855-9_33

Sharma, S., & Kar, S. (2018). Risk management and analysis in hydro-electric projects in India. SSRG International Journal of Civil Engineering, 5(3), 1–7. https://doi.org/10.14445/23488352/IJCE-V5I3P101

Tah, J. H. M., & Carr, V. (2000). A proposal for construction project risk assessment using fuzzy logic. Construction Management and Economics, 18(4), 491–500. https://doi.org/10.1080/01446190050024905

Tang, L., Shen, G., Skitmore, M., & Wang, H. (2015). Procurement-related critical factors for briefing in public-private partnership projects: Case of Hong Kong. Journal of Management in Engineering, 31(6), 04014096. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000352

Thomas, A., Kalidindi, S. N., & Ganesh, L. (2006). Modelling and assessment of critical risks in BOT road projects. Construction Management and Economics, 24(4), 407–424. https://doi.org/10.1080/01446190500435275

Tohumcu, Z., & Karasakal, E. (2010). R&D project performance evaluation with multiple and interdependent criteria. IEEE Transactions on Engineering Management, 57(4), 620–633. https://doi.org/10.1109/TEM.2009.2036159

Valipour, A., Yahaya, N., Md Noor, N., Kildienė, S., Sarvari, H., & Mardani, A. (2015). A fuzzy analytic network process method for risk prioritization in freeway PPP projects: an Iranian case study. Journal of Civil Engineering and Management, 21(7), 933–947. https://doi.org/10.3846/13923730.2015.1051104

Valipour, A., Yahaya, N., Md Noor, N., Mardani, A., & Antucheviciene, J. (2016). A new hybrid fuzzy cybernetic analytic network process model to identify shared risks in PPP Projects. International Journal of Strategic Property Management, 20(4), 409–426. https://doi.org/10.3846/1648715X.2016.1210547

Wang, S. Q., Tiong, R. L. K., Ting, S. K., & Ashley, D. (2000). Evaluation and management of foreign exchange and revenue risks in China’s BOT projects. Construction Management and Economics, 18, 197–207. https://doi.org/10.1080/014461900370825

Wibowo, A., Permana, A., Kochendörfer, B., Kiong, R. T. L., Jacob, D., & Neunzehn, D. (2012). Modeling contingent liabilities arising from government guarantees in Indonesian BOT/PPP toll roads. Journal of Construction Engineering and Management, 138(12), 1403–1410. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000555

Wu, Y., Li, L., Xu, R., Chen, K., & Hu, Y. (2017). Risk assessment in straw-based power generation public-private partnership projects in China: A fuzzy synthetic evaluation analysis. Journal of Cleaner Production, 161, 977–990. https://doi.org/10.1016/j.jclepro.2017.06.008

Wu, Y., Song, Z., Li, L., & Xu, R. (2018). Risk management of public-private partnership charging infrastructure projects in China based on a three-dimension framework. Energy, 165, 1089–1101. https://doi.org/10.1016/j.energy.2018.09.092

Xu, Y., Hu, C., & Chan, A. P. C. (2009). Risk factors for running public private partnerships (PPP) – An empirical comparison between government and private sector. In International Conference on Management and Service Science (MASS’09), Wuhan, China. https://doi.org/10.1109/ICMSS.2009.5301324

Xu, Y., Yeung, J. F. Y., Chan, A. P. C., Chan, D. W. M., Wang, S. Q., & Ke, Y. (2010). Developing a risk assessment model for PPP projects in China – A fuzzy synthetic evaluation approach. Automation in Construction, 19(7), 929–943. https://doi.org/10.1016/j.autcon.2010.06.006

Yu, Y., Darko, A., Chan, A. P. C., Chen, C., & Bao, F. (2018). Evaluation and ranking of risk factors in transnational publicprivate partnerships projects: Case study based on the intuitionistic fuzzy analytic hierarchy process. Journal of Infrastructure Systems, 24(4), 04018028. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000448

Yuan, J. F., Deng, X. P., & Li, Q. M. (2008). Critical risks identification of public private partnerships in China and the analysis on questionnaire survey. In the 4th International Conference on Wireless Communications, Networking and Mobile Computing, Dalian, China. https://doi.org/10.1109/WiCom.2008.2453

Zayed, T., Amer, M., & Pan, J. (2008). Assessing risk and uncertainty inherent in Chinese highway projects using AHP. International Journal of Project Management, 26 (4), 408–419. https://doi.org/10.1016/j.ijproman.2007.05.012

Zhang, C., Liu, X., Jin, J., & Liu, Y. (2016). A stochastic ANPGCE approach for vulnerability assessment in the water supply system with uncertainties. IEEE Transactions on Engineering Management, 63(1), 78–90. https://doi.org/10.1109/TEM.2015.2501651

Zhang, S., Sun, B., Yan, L., & Wang, C. (2013). Risk identification on hydropower project using the IAHP and extension of TOPSIS methods under interval-valued fuzzy environment. Natural Hazards, 65, 359–373. https://doi.org/10.1007/s11069-012-0367-2

Zhao, Z. Y., Tang, C., Zhang, X. L., & Skitmore, M. (2017). Agglomeration and competitive position of contractors in the international construction sector. Journal of Construction Engineering and Management, 143(6), 04017004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001284